Inference Workloads Reshape AI Data Centre Design and Chip Choices
By Kelly Knight 828 views
Inference now accounts for about two-thirds of AI workloads, steering chip design toward lower power use, commodity memory and quickly deployed data centres.

AI infrastructure decisions are increasingly shaped by where and how quickly operators can run inference. Positron AI’s Cameron McCaskill says inference now represents about two-thirds of workloads running through AI infrastructure, compared with about one-third for training. In 2023, he says, the balance was roughly 15% inference and 85% training. That shift changes the practical priorities for new capacity: memory availability, power draw and deployment time matter alongside chip performance.
For IT teams assessing AI capacity, the figures point to a different build profile. Training has often been associated with large clusters, while Positron is targeting inference deployments that can be built in smaller increments. The company’s approach pairs its servers with commodity memory, aiming to avoid dependence on high-bandwidth memory (HBM), which McCaskill describes as expensive and limited in supply. The trade-off is a design choice made for a particular workload and infrastructure model; the available details don't establish how its performance compares with other systems.
Positron's server roadmap
Positron’s first-generation Atlas server uses a programmable chip. The company plans to tape out its own silicon early next year for its Titan server, according to McCaskill. That puts Atlas and Titan at different points in the product roadmap: Atlas is already being prepared for deployment, while Titan is the planned next step with custom silicon.
Oracle is bringing about 340 Atlas servers live in its cloud this quarter, McCaskill said. He also said a neocloud provider has signed on for Atlas and committed to Titan. Those deployments give operators concrete examples of the kinds of cloud and modular environments Positron is pursuing, although the details provided don't identify the neocloud provider or specify the scale of its commitment.
Positron raised $875 million at a $5 billion valuation in September, according to the linked funding coverage. The company is positioning its memory choice as a response to supply and cost constraints in HBM. For teams comparing systems, that makes memory configuration a central part of the evaluation: they’ll want to understand what workload the server is designed for, what memory it uses, and whether the full system meets their capacity and performance needs.
Power and cooling shape deployment options
McCaskill put a single Positron server’s power draw at about 4,500 watts. A full rack of Titan servers, he said, fits within 40 kilowatts. Those figures matter because available power and cooling capacity can set the limits of a deployment before the server count does. Positron says its power profile allows air cooling, which could suit sites that don't have the infrastructure for more demanding cooling arrangements.
That doesn't remove the need for site planning. Operators still need to check the power available to the facility, rack capacity and cooling design against the equipment they intend to install. McCaskill described the target as sites where operators can find a few megawatts of low-cost power. The source provides no site specifications or independent power measurements, so teams should treat the figures as vendor statements to validate against their own deployment requirements.
The proposed footprint also connects to the growth of modular data centres. McCaskill described modular facilities sized at half a megawatt, 1 megawatt or 2.5 megawatts, and said these can be deployed quickly. For operators, smaller facility increments can make it possible to bring capacity online in stages. The fit depends on the site’s power and cooling, the server configuration and the time required to prepare the facility.
The deployment target is monetizable capacity
McCaskill said many inference providers want to get from land and power to monetizable tokens within 90 to 120 days. He sees modular data centres paired with Positron technology as a possible way to meet that target. The timeline is a stated goal, not a demonstrated delivery guarantee: it will depend on the site, equipment readiness and the work needed to connect and operate the facility.
That compressed schedule makes procurement and site readiness important parts of the infrastructure decision. A chip’s specifications are only one piece of the timeline. Operators also need a facility with suitable power and cooling, equipment available when needed, and a deployment plan that fits the size of the intended workload. The source gives no detailed build schedule, so teams should confirm what the 90-to-120-day goal includes before using it to plan capacity.
The shift toward inference is the broader signal to watch. If McCaskill’s workload split reflects the deployments buyers are building for, infrastructure spending will increasingly favor systems that can be placed and powered in smaller sites. Positron is betting that commodity memory, air cooling and modular facilities can help operators bring inference capacity online quickly. IT teams evaluating that model should compare the stated power and rack figures with their own site limits and assess whether the available system details match the workloads they need to serve.